Clients / Projects

 
   
Project : Basement+Ground+Mezanine+30 storeys Building 
For Sheikh Zayed Bin Saqer Al Nahian 


Client : Sheikh Zayed Bin Saqer Al Nahyan 
Consultant : Adnan Saffarini
Contractor : Bin Zayed Contracting Company
Contract Value : 78 Million Dirhams
Our Scope of Work : 
Al Bunian was appointed by the client as a nominated project Management firm to carry out all the planning works for the project. The scope includes but not limited to:
- Prepare construction program
- Prepare resources histograms
- Prepare material histograms
- Prepare cash flow 
- Control the progress of works by updating the program regularly.
- Prepare comprehensive progress report showing the delays (if any) and our suggestions to catch up.
- Any other planning work required by the client in order to control the progress.

Project : National Cadres Development & Recreation Centre at Dubai

Client : Etisalat 
Consultant : Al Turath & Cansult
Contractor : Al Mulla Construction Company
Contract Value : 140 Million Dirhams
Our Scope of Work: 
Al Bunian was appointed by the main contractor (Al Mulla) to carry out all the project planning and control works along the contract period. The scope includes but not limited to:
- Prepare construction program
- Prepare resources histograms
- Prepare material histograms
- Prepare cash flow 
- Control the progress of works by updating the program regularly.
- Prepare comprehensive progress report showing the delays (if any) and our suggestions to catch up.
- Any other planning work required in order to control the progress.

Project : Abu Dhabi Sewerage Scheme, Mussafah New Industrial City 
Sewerage ~ Phase 1 ~ 147/8A

Client : Abu Dhabi Municipality
Consultant : Acer John Taylor & Sons
Contractor : Robodh Contracting Co.
Contract Value : 21 Million Dirhams
Our scope of Work: 
Al Bunian was appointed by the contractor (Robodh) to carry out all the project planning and control works along the contract period. The scope includes but not limited to:
- Prepare detailed construction programme based on CPM.
- Prepare resources histograms (Plant & Manpower)
- Monitor the progress of works by updating the program every two weeks.
- Prepare comprehensive progress report showing the delays (if any) and our suggestions to catch up.
- Any other planning work required in order to control the progress.

Project : Dentistry & Pharmacy Building for Ajman University for Science 
& Technology ~ Ajman 


Client : Ajman University for Science & Technology
Consultant : Eng. Adnan Saffarini
Contractor : Actco General Contracting Co. Ltd.
Contract Value : 24 Million Dirhams 
Our scope of Work: 
We were appointed by the contractor (Actco) to carry out all the project planning and monitor the progress along the contract period. The scope includes but not limited to:
- Prepare a detailed construction program based on critical path method (CPM) through the software PRIMAVERA(r) for Windows(r) version 2.0. The program will cover the main contractor and sub-contractors works as well procurement schedule.
- Prepare Manpower Histogram.
- Prepare Cash flow.
- Visit the site, check progress and receive updating data from the site staff every two weeks.
- Input the data and reschedule the original program.
- Check the resulted updated program in order to validate/
re-adjust the new critical path.
- Provide the contractor with a print out showing the actual program compared with the target program.
- Prepare a detailed progress report every two weeks or whenever requested, in which we report the situation of the progress of main and sub-contractor and pointing out the reasons behind the delay of each activity (if any) and give suggestions to cover the delays.

Project : R-488 Improvement of Sheikh Zayed road

Client :
Dubai Municipality
Consultant : Italconsult
Contractor : Dutco Balfour Beatty
Contract Value : 110 Million Dirhams
Our Scope of Work: 
Acting as project management consultant for Italconsult. One of our major tasks was to analyze & evaluate the contractor program of work to be sure that it is logical, practical and achievable.

Project : Low cost income housing project PJ 1088 & PJ 1089

Client :
Dubai Municipality
Consultant : Atturath
Contractor : Bartawi Contracting Co.
Contract value : 40 Million Dirhams
Our scope of work : 
Acting as project Management consultants for Atturath. Our 
Main Tasks is to evaluate and analyze the construction program submitted by the contractor.

Project : Road from Twam R/A to Zaker R/A (Al Ain)

Client : Al Ain Municipality
Consultant : Acer Freeman Fox
Contractor : Al Dhafra International Group
Contract Value : 36 Million Dirhams
Our Scope of work : 
Prepare the planning package for the contractor. 
i.e. construction program, manpower histogram and cash flow.

Project : Sajaa-Khwaneej Highway

Client : Ministry of Public Works & Housing
Consultant : Nespak
Contractor : Seif Bin Darwish
Contract Value : 39 Million Dirhams
Our Scope of work : 
Acting as Project Management Consultant for Nespak. The
Scope includes but not limited to :
- Analyze & evaluate the contractor's Program of work to 
be sure that it is logic, practical and achievable.
- Analyze & evaluate the contractor's extension of time 
claims.

Project : Al Bateen Palace (Abu Dhabi)

Client : H.H. Sheikh Hamdan Bin Zayed Al Nahian
Consultant : Ghazi Awad consultant engineers
Contractor : Rizzani De Eccher
Contract value : 56 million Dirhams
Our scope of work : Prepare extension of time claim for the contractor.

Project : Doha Airport approach road
Client : Ministry of Public works (Qatar)
Consultant : Ital Consult
Our scope of work : 
Prepare a program of conceptual and final design activities. 
This Program was submitted by Ital consult to the client as part of their pre-qualification document.

Project : Dubai Port authorities Camp Phase 3

Client : Dubai Ports Authorities
Consultant : Rice Perry Ellis
Contractor : Arabtec
Contract value : 23 Million Dirhams
Our scope of work : 
Prepare extension of time claim for the contractor.

Project : Expansion of Sewerage treatment plant no. 4 at Jebel Ali Port

Client : Dubai Ports Authorities
Consultant : Parson Engineering Science
Contractor : Arabtec 
Contract value : 8 Million Dirhams
Our scope of Work : Prepare the planning package for the contractor. i.e. 
Construction Program, resources histogram & cash flow, and then update the program every two weeks and prepare progress report.

Project : Building for H.H. Sheikh Khalid Bin Abdul Aziz Al Qasmi at
Garhoud (Dubai)


Client : H.H. Sheikh Khalid Bin Abdul Aziz Al Qasmi.
Consultant : Al Emara Al Khalijia Consulting
Contractor : Emirates Trading Company (ETA)
Contract Value : 14 Million Dirhams
Our scope of Work : 
Acting as project Management consultant for Al Emara Al 
Khalijia. Our task is to coordinate between the different sub contractor and produce a construction program, then update it regularly and monitor the project to be sure that it will be completed the contract time.

Project : Chicago Beach Resort Development Tower Hotel 
Back of House Fit out & Finishes (Contract No. 1445)


Client : H.H. Sh. Mohamed Bin Rashid Al Maktoum
Consultant : W.S. Atkins 
Contractor : Arabtec Hotel Interior Division
Contract Value : 16 Million Dirhams
Our scope of Work : 
Prepare the planning package for the contractor. 
i.e. Construction Program, Manpower Histogram & 
Cash flow.

Project : Emirates Tower (Twin Tower) on Shk. Zayed Road, Dubai

Client : H.H. Shk. Mohamed bin Rashid Al Maktoum
Consultant : D S I 
Contractor : Al Habtoor Marble Co. (Stone works)
Contract Value : 27 Million Dirhams
Our scope of Work: 
Al Bunian was appointed by the contractor to carry out all the planning works for the project. The scope includes but not limited to:
- Prepare construction program
- Prepare resources histograms
- Prepare material histograms
- Control the progress of works by updating the program regularly.
- Prepare comprehensive progress report showing the delays (if any) and our suggestions to catch up.

Project : Sewerage & SW Trunk Lines ADSS, Tender No. 219/B

Client : Abu Dhabi Municipality
Consultant : Acer John Taylor & Sons
Contractor : Robodh Contracting Co.
Our scope of Work : 
Preparation of Planning Package (Tender stage) which included the following :
- Master Programme
- Labour Histogram
- Machine Histogram
- Cash Flow

Project : Sewerage & SW Trunk Lines ADSS, Tender No. 218/B

Client : Abu Dhabi Municipality
Consultant : Acer John Taylor & Sons
Contractor : Robodh Contracting Co.
Our scope of Work : 
Preparation of Planning Package (Tender stage) which included the following :
- Master Programme
- Labour Histogram
- Machine Histogram
- Cash Flow

Project : Y2K Project Plan

Client : Gulf Test Factory Services
Our scope of Work: 
GTFS is one of the leading IT companies in Dubai. The main activity of GTFS is to solve the Year 2K problem.
Since all Y2K projects have a strict deadline, it was necessary for GTFS to seek the services of a professional project management company to carry out the required project planning works.
The scope of work of ALBUNIAN includes but not limited to the following:
- Provide extensive professional training on Project Management and Planning for GTFS senior staff. The training include to use the planning software to carry out planning tasks. 
- Prepare detailed programme for Year 2K crises project.
- Provide auditing services on project plans prepared by GTFS staff.

 